Latest News

Construction Notice – Apartment Row Street Work

 

Contractors on behalf of Golden State Water Company (GSWC) will be starting a large-scaled street project in Apartment Row. The project includes the replacement of the existing main line, existing services, and fire hydrants. Construction is set to begin on Monday, November 5th (work will not be taking place on Election Day). This project is expected to extend through the middle of April 2019. The following table provides a breakdown of construction dates and affected streets. Please note, the schedule is subject to change:

Click here to view the complete Construction Notice from GSWC

Area of Construction Length of Time for Construction
Green Avenue – From Bloomfield & Noel November 7 through December 7
Green Avenue – From 4351 Green to Lexington December 10 through January 10, 2019
Howard Avenue – From 3921 Howard to Howard Plant January 11, 2019 through February 22, 2019
Farquhar Avenue February 25, 2019 through March 29, 2019

 

Print Friendly, PDF & Email
0
City Hall is closed every other Friday. Please check out our calendar to see the schedule. Click here.